You are the project manager on a defense project and are creating a network diagram. Task A (3… 1 answer below »

You are the project manager on a defense project and are creating a network diagram. Task A (3 days) and Task B (6 days) can start immediately. Task C (2 days) can start after Task A is complete. Task D (1 day) and Task F (2 days) can start after Task B is complete. Task E (4 days) can start after Task C and Task D are complete. Task G (5 days) can start after Task D and Task F are complete. When Task E and Task G are complete, the project is finished. What is the critical path?